The past 2 weeks have been the most exciting for us thus far. Walking in to the once barren space, has now evolved in to a pretty striking skeleton of the pub. Amazing how throughout the many phases of construction, how one’s perception of size and spatial relationships fluctuates as we go: first the space was HUGE!, then got trenched and felt smaller, then framing went up and drew our attention to the height of the walls, then as framing progressed we realized the “coziness” of certain areas we never actualized before- in a good way!
Here’s what we’ve been able to accomplish this week on the construction-end:
* Mezzanine/ brewery cold room framed
* In-wall electrical & plumbing rough
* In-wall blocking
* In-wall inspections (passed)
* Frame Furrdowns for “Event” area and above “bar”
* Overhead electrical/ mechanical/ plumbing/ gas rough
* Air handlers & condensers set on roof
* Electrical & pull wire initial set
* Hollow metal frames set
* First-side sheetrock on “behind bar” area, “dartboard” wall, and mezzanine!
In the coming weeks, we can expect wrapping up sheetrock installation, wallboard inspection, and getting the air ON! so we can begin the tape & floating for the walls!
If you are ever in the area, please don’t hesitate to “drop-in,” put on a hard-hat and take a quick tour of the space. Our internal office is across from the brewpub, within the development, in suite #3103.
Remember to sneak-a-peek of our construction progress HERE at our gallery on facebook. It is truly exciting to see what you all have contributed and continue to contribute to aid in making all this happen!!! Thank you for your continued support!
-Karinne